logo_tag
Back

Dubai Awards AED56.5 Billion in New Al Maktoum International Airport Contracts, Lifting Total to About AED80 Billion

Why It MattersAwarding terminal, concourse and power packages together, after earlier enabling and systems awards, shows how a greenfield hub is delivered: sequential, parallel-site contracting that commits the programme before any passenger operations.

Zawya

What happened

A further series of contracts worth AED56.5 billion ($15.4 billion) has been awarded for the development of Al Maktoum International Airport in Dubai. The awards expand the construction programme across passenger terminals, concourses, transport infrastructure, power systems and other airport facilities.

Dubai Awards AED56.5 Billion in New Al Maktoum International Airport Contracts, Lifting Total to About AED80 Billion

The newly awarded work covers substructure and associated infrastructure for the West Terminal Building, Concourse 1 and Concourse 4. It also covers superstructure, architectural and building systems works for Concourses 2 and 3, and major electrical power infrastructure including principal substations.

The West Terminal Building and Concourse 1 packages include basements, underground tunnels, access ramps, short-term car parks, the Ground Transportation Centre, metro interface works, landside bridges, underground GSE circulation corridors, the principal BHS backbone network and utilities such as electrical power, water supply, telecommunications, sewerage and stormwater drainage. The Concourse 2 and 3 superstructure packages cover the main concourse buildings, rotundas, structural steel bridges, supports for passenger boarding bridges, large-span steel roof spaceframes, façades and roofing.

In the preceding phase, Dubai Aviation Engineering Projects awarded contracts and packages worth approximately AED23.815 billion, covering enabling works, substructure packages, the Automated People Mover and Baggage Handling systems. With the new awards, total contracts and packages awarded to date reach approximately AED80 billion.

Progress on site and official statements

Dubai Aviation Engineering Projects said enabling works in the Concourse 2 and Concourse 3 zones and the central area of the site are nearing completion, while work continues in the central passenger terminal zone and the Concourse 4 area.

Total excavation exceeds 24.23 million cu m, backfilling exceeds 5.2 million cu m and 7,635 piles have been completed. Across the Concourse 2 and 3 substructure packages, more than 875,603 cu m of concrete have been placed and over 226,270 tonnes of reinforcement steel installed. The combined workforce across these packages is approximately 14,000 people.

Sheikh Hamdan said the contracts are a significant step in developing Dubai's new global aviation hub and will strengthen the emirate's capacity for sustained passenger and cargo growth, in line with the Dubai Economic Agenda, D33, which aims to double the size of Dubai's economy. Sheikh Ahmed said Phase One is moving ahead in accordance with the approved programme, with the delivery sequence structured to sustain parallel progress across multiple sites.

Industry impact & what to watch

The sequence here is typical of how a greenfield hub is procured: enabling works and systems such as the people mover and baggage handling go first, then substructure, then superstructure and power. With roughly AED80 billion now committed, the programme has moved from site preparation into building the passenger-facing structures themselves.

For suppliers across steel, façades, building systems, electrical equipment and ground-handling infrastructure, awards of this kind set the pace of demand over the coming construction years. The parallel-site delivery approach Sheikh Ahmed described concentrates that demand across several concourses at once rather than spreading it out.

The next markers are the completion of enabling works in the Concourse 2 and 3 zones and the central area, which are described as nearing completion, and continued progress in the central terminal and Concourse 4 areas.

Original Source

Massive $15.4bln contracts awarded for Al Maktoum International Airport | ZAWYAZawya
Keep Exploring