Guernsey Deputies Approve Up to £6.1m for Storm-Damaged Airport Terminal Roof Repairs

Why It MattersAirport terminal envelopes are long-life assets whose storm damage can turn temporary fixes into multi-year capital programmes, leaving small island airports carrying scaffolding costs and construction disruption at the passenger front door.

BBC

What happened

Deputies in Guernsey have agreed to spend up to £6.1m to repair the roof of the terminal building at Guernsey Airport, which was damaged by high winds during several storms. Scaffolding went up in 2025 as a result of the damage.

Guernsey Deputies Approve Up to £6.1m for Storm-Damaged Airport Terminal Roof Repairs

The States' Trading Supervisory Board said "extensive structural repairs" could take up to 18 months. The board wants repairs to begin by mid-2027, with a specific timeline and costs to follow expressions of interest from potential contractors.

Deputy Mark Helyar, president of the board, called the scaffolding "unsightly, unwelcome at our front door, and has already cost the island some £165,000". He added that it is "not a solution, but merely treatment of a symptom of the deteriorating roof". According to Helyar, the full repair should restore the roof's wind resistance, give it a further 20 years of design life and allow the permanent removal of the scaffolding.

Industry impact & what to watch

Terminal roofs sit outside most airport resilience planning until weather exposes them, and Guernsey's case shows how a building-envelope problem can outlast the storms that caused it. Scaffolding installed in 2025 is still in place, and the repair programme will not start before mid-2027. That gap between damage and cure is a recurring cost for an airport operator, because interim measures carry their own bills and their own visibility to passengers.

The £6.1m figure is a ceiling set before contractors have been engaged. The board has said a specific timeline and costs will follow expressions of interest, so the number that counts will be the one that emerges from that process. For a small island airport, a repair spanning up to 18 months also raises a practical question about how the terminal keeps operating around structural works.

The next milestone is the contractor interest exercise. Its outcome will show whether the mid-2027 start and the 18-month duration hold, and what the scaffolding costs the island in the meantime.