Both Mumbai Airport Runways Closed 11:00–17:00 IST on 19 November 2026 for Annual Post-Monsoon Maintenance

Why It MattersA fixed six-hour annual shutdown of a two-runway airport forces airlines and cargo handlers to plan around zero movements, and belly cargo on scheduled passenger flights absorbs the disruption alongside passengers.

Logisticsinsider

What happened

Both cross runways at Chhatrapati Shivaji Maharaj International Airport (CSMIA) in Mumbai were non-operational from 11:00 to 17:00 IST on 19 November 2026 for the airport's annual post-monsoon runway maintenance. Mumbai International Airport Limited (MIAL), which operates the airport, announced the six-hour window in a passenger advisory on its official X account on 31 October 2026. The advisory named runways 09/27 and 14/32 as the two closed.

Both Mumbai Airport Runways Closed 11:00–17:00 IST on 19 November 2026 for Annual Post-Monsoon Maintenance

MIAL said it started coordinating with airlines and other stakeholders six months ahead so that flight schedules and manpower planning could be synchronised, and that a Notice to Airmen (NOTAM) had been issued in advance. The work covers detailed inspections, surface repairs and technical assessments of runway lighting, markings and drainage systems. MIAL described the shutdown as an annual post-monsoon practice meant to keep the airport's infrastructure in line with global standards and to support operational continuity and passenger safety.

With both runways shut, no aircraft could land or take off at CSMIA during the window. On 18 November, Akasa Air said some of its flights to and from Mumbai had been affected by the closure and asked passengers to check their flight status. Cargo carried in the belly of passenger aircraft scheduled in the window is also affected. In its sustainability report for the financial year 2026, MIAL said CSMIA handled 753,855 tonnes of cargo in the reporting year, 77.8% of it international, and that more than half of that volume travelled as belly cargo on passenger flights.

The closure follows a similar six-hour post-monsoon shutdown on 20 November 2025. Comparable six-hour closures were also carried out on 17 October 2024, 17 October 2023 and 18 October 2022.

Industry impact & what to watch

A two-runway airport that closes both runways at once has no fallback: every scheduled movement inside the window either moves out of it or is cancelled. That is why MIAL's lead time matters. Six months of coordination is what lets airlines rebuild rotations and lets ground crews be rostered around a quiet period instead of improvising on the day.

For cargo, the exposure sits mostly in the passenger fleet. With more than half of CSMIA's cargo tonnage carried as belly freight, a gap in passenger departures is also a gap in uplift capacity, and shippers booked on those flights have to be re-accommodated on earlier or later services. Forwarders working Mumbai routinely build the annual closure into their November planning.

The dates themselves show a pattern: the window has moved from mid-October in 2022 to 2024 to the third week of November in 2025 and 2026. Whether MIAL publishes the next closure date as early as it did this time, and whether that date shifts again, is the detail that cargo and airline schedulers will look for in next year's advisory.

Original Source

Mumbai Airport Runway Closure Today From 11 am to 5 pmLogisticsinsider