Chios Homer Airport to Close to Scheduled Flights for Four Months for Runway Works
Why It MattersA planned multi-month shutdown of a single-runway island airport shows how off-season construction windows are used to protect summer capacity, shifting the burden onto surface and sea links that carry winter demand.
What happened
The eastern Aegean island of Chios will have no scheduled commercial flights from Nov. 15, 2026, to March 15, 2027. Work to expand the maneuvering area at Homer Airport will close its sole runway for the duration.

The closure dates were confirmed in a transport ministry document presented on Wednesday evening at an emergency meeting of the Chios municipal council.
The works combine the second and third phases of the airport expansion project. Authorities say the schedule is intended to improve construction safety, limit weather-related delays and ensure that air links are available ahead of the 2027 summer season.
Industry impact & what to watch
Closing a runway outright, instead of phasing work around live operations, is the usual trade-off at single-runway regional airports: construction is faster and safer, but the airport loses all scheduled service for the period. Placing that gap in the winter months, when island traffic is lowest, protects the summer season that carries most of the revenue for carriers and local businesses.
For airlines serving Chios, a four-month suspension means a full withdrawal and later relaunch of schedules, not a reduced timetable. The ahead-of-summer completion target is the commitment that matters most, since the 2027 summer schedules will be built around it.
The next milestone is the March 15, 2027 reopening date: any slippage in the combined second and third phases would eat directly into the lead time carriers need to restore service for the summer season.